Electric garbage trucks are one of the best fits for an electric heavy vehicle. They run short, fixed rounds, stop hundreds of times a day, come back to the same depot every night and sit idle overnight. This page tracks how they are actually performing on council and operator rounds, newest first, so you can plan the charging, the site supply and any solar from real results rather than brochure range.
Last checked: 17 November 2026. Case studies cover the last two years, and we add new ones as results are published. Figures marked "our calculation" are worked out from the published numbers, not stated by the source.
The short answer
| Measure | What the results show |
|---|
| Battery left after a normal round | Often 35% to 60% |
| Typical daily distance | 80 to 160 km in cities and suburbs, up to 190 km on long rural rounds with a mid-day top-up |
| Energy per 8-hour round | About 150 to 250 kWh from the battery for a heavy truck (19 t to 27 t) |
| Energy per km | About 1.6 to 2.5 kWh/km, more on hard, fully loaded days |
| Typical battery | 200 to 400 kWh |
Most trucks finish a single shift with charge to spare. The ones that struggle run long days, heavy loads or extra duties on a battery sized for an average day.
The energy figures (kWh per round and per km) come from the two largest measured studies to date: Cenex's data from 24 Dennis Eagle eCollect trucks across five Welsh councils (2023) and the California Energy Commission's side-loader demonstration (2024). Most newer case studies report range and battery left rather than kWh.
Case studies, newest first
October 2026British Columbia, CanadaFell short
District of North Vancouver
- VehicleOne pilot electric garbage truck
- TrialOct 2024 to May 2026
- Needed help to finish35% of days
- Ended below 10%17% of days
The council is sending the truck back. Staff put it at about 70 to 75% of a diesel truck's work, mostly because the battery ran short. Fuel costs were about 82% lower and maintenance about 63% lower, but it wasn't doing the same workload.
Source: North Shore Local, 4 October 2026
September 2026Brisbane, AustraliaTrial
Remondis Australia
- VehicleMercedes-Benz eEconic 6x2
- Battery300 kWh
- RangeAbout 150 km
Trialled in August 2026 with a Superior Pak body. Remondis runs about 600 collection trucks in Australia and is weighing electric, hydrogen and hybrid options.
Source: The Driven, 28 September 2026
July 2026Melbourne, AustraliaWorked
City of Casey
- VehicleElectric compactor trucks
- Fleet6 trucks from July 2026
- Running since2019
Casey has used electric compactors on hard waste since 2019, with three trucks until mid-2026. The service now runs a fleet of six, with diesel trucks only as back-up.
Source: City of Casey
February 2026The Bronx, New York, USWorked
Royal Waste Services
- VehicleMack LR Electric
- Battery376 kWh
- Charger150 kW
- CollectedAbout 68 tonnes a week
No downtime in the first eight weeks, according to Mack. Three more trucks are on order.
Source: Mack Trucks, Electrek, 21 February 2026
December 2025California, USMixed
City of Sacramento
- VehicleMack LR Electric side loader
- Battery376 kWh
- Daily distance130 to 160 km
- PayloadAbout 7 US tons (gas trucks about 9)
Runs 5 days a week with two trips to the tip. DC charging reaches 80% in about 90 minutes, but it's usually left on charge overnight. The lower payload put it on a lighter recycling round.
Source: Mack Trucks, December 2025
November 2025GermanyWorked
City of Karlsruhe
- VehicleMercedes-Benz eEconic
- Fleet18 trucks
- RoundAbout 80 km, 60 stops
- Battery usedAbout 35%
In service since September 2025. The trucks finish a shift at 64 to 65% with no charging during the day.
Source: Electrek, 19 November 2025
November 2025UKWorked
Salford City Council
- VehicleMercedes-Benz eEconic 27 t
- Battery left after a round40 to 60%
- Longest day97 km, 30 t, 36% left
The first electric truck in a 36-truck fleet. It finished every round on one charge. These are the maker's figures.
Source: Daimler Truck UK, 13 November 2025
August 2025NetherlandsOrder
City of Amsterdam
- VehicleDAF XD Electric
- Fleet40 trucks, delivered in 2026
- Battery315 kWh (3 x 105 kWh LFP)
- Body power90 kW electric PTO
The order covers rear loaders, crane and hook-lift trucks and front loaders.
Source: electrive, 20 August 2025
August 2025Chicago, USOrder
Republic Services
- VehicleMack LR Electric
- Fleet2 trucks
- Battery376 kWh
- Charging150 kW DC, under 2 hours
Charged nightly. The local network's rebate program helped pay for the connection work.
Source: Electrek, 15 August 2025
July 2025Scotland, UKTrial
Orkney Islands Council
- VehicleOne electric refuse truck
- Longest day190 km
- Charger160 kW at the depot
- Trial cost£277,000
Long rural rounds from Kirkwall, topped up during breaks: 50% to 75% at morning tea and 40% to 100% at lunch. The cost covers the truck lease, charger and site works.
Source: Orkney Islands Council, 7 July 2025
Trials still to report in Australia
Blacktown, Blue Mountains and Sutherland councils in NSW, councils in Adelaide with Cleanaway, and JJ's Waste and Recycling on the Sunshine Coast have all trialled electric garbage trucks. We haven't found published results yet.
What changes the energy use
- The body - the bin lifter and compactor can double the energy per km on a heavy, fully loaded day. In a California trial (2024), the truck used about 3 kWh/mile empty and over 6 kWh/mile with heavy hydraulic use. Electric bodies use less than hydraulic bodies driven from the battery.
- Weather - data from 24 trucks in Wales (2023) showed a large gap in range between winter and summer days. In most of Australia, cabin air-conditioning on hot days is the bigger load to allow for.
- Hills and driving style - both made a noticeable difference to range in the Welsh data, more so on longer rural rounds.
- Urban or rural - urban rounds have more bins over fewer km, so they use more energy per km. A rural round covers more km with fewer stops. Per day, the two came out about the same in the Welsh data.
- Trips to the tip - a long run to the transfer station or landfill adds highway km, which suits an electric truck less well than the stop-start collection itself.
- Long days and extra duties - a round that runs well past 8 hours, or extra jobs on top of collection, can push a day beyond what the battery holds. North Vancouver's pilot truck fell short for this reason.
Planning the charging
For a heavy garbage truck on a normal 8-hour round, plan on about 200 to 250 kWh from the grid each working day, allowing about 10% for charging losses. A 40 kW depot charger puts that back in about 5 to 6 hours, so overnight charging covers a single-shift round. Fast DC charging is only needed for double shifts, long rounds or a top-up between loads, as on Orkney.
Ten trucks on overnight charging add about 2,000 to 2,500 kWh a night and up to 400 kW of load. Check whether your site supply can carry it and how demand charges affect the bill, and use load management to spread the charging across the night.
Can solar cover it?
Our estimate, for Sydney: a fixed rooftop system produces about 3.9 kWh per kW of panels per day across the year (about 2.4 in winter). One garbage truck using about 210 kWh a day, 260 working days a year, needs about 40 kW of solar to make as much energy over a year as the truck uses. That takes roughly 200 m² of roof per truck.
Garbage trucks mostly charge overnight, when solar isn't producing. So the solar either covers other site loads by day, gets exported, or charges a battery that then charges the trucks at night. A battery to shift a full night of truck charging is large, about 150 kWh or more per truck, and overnight grid power is usually the cheapest of the day. Before buying a battery for this, check your tariff, and move as much truck charging into the day as your rounds allow. See solar and batteries for fleets.
Before you decide
- Log your rounds - km, hours, bin lifts, tonnes and trips to the tip for each truck over a few weeks, including your hottest and busiest days.
- Size for the hard days - pick a battery that still leaves a margin on the longest round in summer, not the average one.
- Check the payload - batteries add weight. In NSW, zero-emission heavy vehicles can carry extra axle mass (see electric trucks in Australia).
- Plan the depot early - chargers, supply upgrades and approvals can take longer than delivery of the trucks.
- Trial first - most fleets in these case studies started with one truck before ordering more.
See also electric trucks in logistics and electric vans and commercial fleets.